Post-Fire Drainage & Erosion Control
After a wildfire, burned slopes send water down fast and carry dirt and debris with it. We get culverts, ditches, cross-drains and water bars ready for it, and put erosion control on bare ground above buildings and roads, before spring melt. It's all machine work. We're based in 100 Mile House and work across BC.
Why burned ground floods
Before a fire, the trees catch rain and the needles and duff on the ground soak it up. After a hot burn, that's gone. The ground is bare, a lot of it is ash, and some burned soil sheds water for a while instead of taking it in. Rain and snowmelt run off faster and in bigger volumes than the old drainage was built for.
That water finds the weak spots. Culverts plug with ash, soil and burnt wood. Ditches fill in. Runoff cuts gullies down access roads and across slopes, and on steep burned ground it can turn into a debris flow.
The province's post-wildfire guidance names heavy bursts of rain as the most common trigger, and fast spring snowmelt can set it off too. It says the risk on severely burned ground can last two years or more.
Around Clinton, the Thompson-Nicola Regional District said in November 2026 that flooding and debris-flow risk can stay high for one to two years after a fire like Pear Lake. Our Clinton page has the details on that fire and where things stand.
What we build before the melt
We keep water in channels that can carry it, and keep it away from buildings, roads and soft slopes.
Culverts
We clean out plugged culverts and replace damaged ones. Where a culvert was sized for the runoff before the fire, we upsize it for what comes off the burned slope now, and armour the inlet and outlet so the water doesn't eat around it.
Ditches
We clean out ditches and re-cut them to grade so they carry water instead of filling up with ash and soil, and armour them with rock where the water runs hard.
Cross-drains and water bars
We cut cross-drains and water bars into access roads, driveways, trails and old fireguard, so water comes off the surface before it builds up instead of running the whole length and washing it out.
Slopes above buildings
We turn runoff away from buildings, wells and yards with berms, diversion ditches and recontouring where water concentrates on bare ground, and pull burnt debris out of the channels it would plug.
This is machine work. We don't do seeding or hydroseeding. If a slope needs it, we'll tell you so you can line it up with someone who does.
If a culvert has already failed or a road has already washed out, that's emergency work. Call any time, same-day mobilization.
From site walk to ready for spring
- 01
Walk the water
We walk the property with you and follow the water: where it comes from, where it crosses your roads, what it's pointed at. Every culvert, ditch and low spot gets looked at.
- 02
Written scope
You get a written estimate with a defined scope.
- 03
Permits first
If any of the work is in a creek, we handle the Water Sustainability Act notification or approval before a machine goes near it.
- 04
The work
Danger trees along the work area come down first, and where WorkSafeBC requires an assessment, a certified danger tree assessor does it. Then we build the culverts, ditches, cross-drains and erosion control, and check them.
- 05
Walk-through
Once it's done, we walk it with you.
Creeks, permits and when to call an engineer
Work in and around a creek falls under BC's Water Sustainability Act, and that includes a creek that only runs in spring. Replacing a culvert in a stream needs either a notification at least 45 days before the work or an approval, depending on the job. A roadside ditch that only carries runoff usually isn't a stream under the Act. We check which applies and handle the notification or approval before we dig.
If a slope above your buildings shows signs of debris-flow risk, get a geotechnical engineer to look at it before anyone builds anything. The province's post-wildfire guidance points owners to geotechnical specialists for exactly this. We build what the engineer designs. On Crown land and road rights-of-way, the work needs authorization from whoever manages that land.
The rest of the recovery work
Drainage is one part of wildfire risk reduction.
Drainage after a fire — straight answers
How long does flood risk last after a wildfire?
On severely burned ground, the province says the risk can last two years or more. Around Clinton, the TNRD said in November 2026 that flooding and debris-flow risk can stay high for one to two years after the Pear Lake fire. Heavy bursts of rain are the most common trigger, and fast spring snowmelt can set it off too.
Do I need a permit to replace a culvert?
If the culvert is in a creek, yes. Replacing a culvert in a stream falls under the Water Sustainability Act and needs a notification at least 45 days ahead, or an approval, before it starts, even if the creek only runs in spring. A culvert under a driveway that only carries ditch runoff usually doesn't. We handle that paperwork before the work is scheduled.
Can drainage work be done in winter?
A lot of it can. Frozen ground carries machines onto ground that's too soft in the shoulder seasons, and culverts and ditches can be cleaned out and rebuilt as long as the ground and the weather let us. The aim is to have it done before spring melt.
Do you do seeding or hydroseeding?
No. Our erosion control is machine work: drainage, diversions, berms, recontouring and clearing debris out of channels. If a slope needs seeding, we'll tell you and you can line it up with someone who does it.
Has anyone assessed the burn area for debris-flow risk?
After a large fire, the Ministry of Forests can do a post-wildfire natural hazard risk analysis that maps the areas at higher risk of debris flows, flooding and landslides. For the Pear Lake fire, the preliminary report is posted on the TNRD's website. It's a good place to start before you plan drainage work.
Who pays for drainage work on private land after a fire?
Generally the landowner. The province's post-wildfire guidance says the cost of mitigation falls to the owner of whatever is at risk. Damage caused by fire suppression work can be different, so if guard or suppression work crossed your land, ask BC Wildfire Service about rehabilitation first.
What should I check on my property before spring?
Walk every culvert and look for ash, soil or burnt wood in the inlet. Look for ditches that have filled in, and burned slopes that drain toward your buildings, well or road. A culvert or ditch that was barely keeping up before the fire has more water to handle now. If you're not sure what you're looking at, call and we'll come walk it with you.
Talk to us about drainage on your property
- 1.Tell us about the ground — five minutes.
- 2.We walk it with you and talk through what's urgent, what can wait, and rough numbers.
- 3.You get a written estimate with a defined scope. If we're not the right fit, we'll say so and point you at who is.
Call or text 250-329-7356 to speak directly with the owner. Or send the project through the form and we'll respond within one business day.